PROJECT DEVELOPMENT

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A project starts with a need that has to be fulfilled for a clearly defined customer or Project Owner in project speak. Below we walk you through a typical biogas project framework;

 

STAGE 1 : INITIAL CUSTOMER INTERACTION

  • Details of operations
  • Existing waste disposal costs
  • Existing energy costs
  • Limited tests on substrate

 

Customer will be asked to supply a detailed project write-up and to share their own work as a benchmark. At this stage limited testing may be required and these cost to be borne by customer.

 

STAGE 2 : DESKTOP STUDY

  • Initial option development
  • Preliminary Fatal Flaw analysis
  • Preliminary feasibility calculation
  • Review

 

The desktop study is done at risk for qualifying projects. A qualifying project is one that is adopted by one of our team who sees sufficient merit to become its project driver.

 

50%

The output level of the proceeding stages is that of Business Case, i.e. establishment of an “order of magnitude” budget with limited architecture development.

 

 

STAGE 3 : WORK PACKAGE 1 - Project Architecture & Feasibility

  • Project Deliverables
    • Waste streams & disposal strategies
    • Biogas Production
    • Energy Deployment
    • Discharge Standard
    • Process Water
  • Client Confirmation of Parameters
  • Plant Design & Preliminary Drawings
  • Project Costing
  • Financial Feasibility

 

The focus of Work Package 1 is the development and refinement of the Project Architecture, a unique sustainable solution. Outputs include detailed costing, risk analysis and financial viability.

 

70%

The output level of stage 3 is that of Prefeasibility.

 

 

STAGE 4 : WORK PACKAGE 2 – Appointment of an Environmental Practitioner

Obtaining the necessary environmental permissions & permits may be a long lead-time item whilst impacting on design considerations.

 

STAGE 5 : WORK PACKAGE 3 – Engineering Development

  • Detailed Testing
  • Waste Testing
  • Energy Logging
  • Engineering Review & Optimisation
  • Construction Drawings
  • Final Price Determination
  • Review

 

The focus is on risk reduction & mitigation.

 

85%

The output level of this stage is that of Feasibility level.

 

STAGE 6 : FINAL CONTRACT NEGOTIATION

 

STAGE 7 : IMPLEMENTATION

 

WORK PACKAGE 4 – Implementation Engineering

WORK PACKAGE 5 – Construction

 

95%

The output level of this stage is a complete plant.

 

STAGE 8 : Start-up & Handover

WORK PACKAGE 6 – Start-up

  • Plant Optimisation
  • Final Commissioning
  • Training

 